Poor supervision of a building contract

Poor supervision of a building contract can have serious financial consequences

If you have a claim arising from poor supervision of a building contract then call us for a free case assessment and details of no win, no fee funding. Call 0333 888 0404 or email us at [email protected]

Anybody involved in a build project will undoubtedly have heard of a JCT Contract.  In fact, a suite of contracts have been prepared by the Joint Contracts Tribunal. They are designed to “facilitate the process of delivering a building project. In simple terms they set out the responsibilities of all the parties within the process and their obligations to each other”.

One of the recommendations in a JCT Contract is the appointment of a Contract Administrator (known as a Project Manager under NEC Contracts) to act as the client’s representative throughout the project and oversee the works.  Customarily, the role will go to the likes of a surveyor or an architect, but it can be any number of professions.
The work they undertake will invariably be to:

  • invite and process tenders;
  • oversee construction progress;
  • co-ordinate with site inspectors;
  • identify and agree defects;
  • issue the various certificates required; and
  • generally act as liaison between all the parties.

Their brief can be as wide or as limited as the client wishes, but if a Contract Administrator or Project Manager fails to supervise or administer the contract, things can go seriously wrong.

Among the problems arising from poor supervision of a building contract are:

  • Failure to ensure the contract is signed;
  • Failure to notice or report on building defects;
  • Failure to comply with the timetable;
  • Biased decisions;
  • Allowing an overrun on costs;
  • Negligently issuing Interim or Final Certificates;
  • Failure to ensure insurance was in place; and
  • Recommending unreliable contractors.

All of those (and more) could be considered negligent.

And where there is negligence, invariably a financial loss will result. An overrun on the project; additional build costs; inability to recover against the main contractor; having a build fail due to incompetence are all factors that are likely to have far reaching costs consequences for the client.

If you suffer financial losses exceeding £10,000 due to poor supervision of a building contract then call us for a free case assessment on 0333 888 0404 or email us at [email protected]

Lee Dawkins

Lee Dawkins

Over the past 30 years Lee has overseen the expansion of the firm’s litigation department. He developed our personal injury and clinical negligence teams, creating various niche areas that now enjoy a national profile. He pioneered contentious probate, setting up one of the UK's leading inheritance dispute teams and established Slee Blackwell as a force within claimant professional negligence. He now works as the firm's marketing partner.
Lee Dawkins

Lee Dawkins

Over the past 30 years Lee has overseen the expansion of the firm’s litigation department. He developed our personal injury and clinical negligence teams, creating various niche areas that now enjoy a national profile. He pioneered contentious probate, setting up one of the UK's leading inheritance dispute teams and established Slee Blackwell as a force within claimant professional negligence. He now works as the firm's marketing partner.

Share this post:

Share this post:

Call the Slee Blackwell helpline on 0333 888 0404